Mantashe confirms 45- to 60-day delay in renewables bidding to cater for doubling of procurement to 5 200 MW

- Advertisement -spot_img

Must read

MINERAL Resources and Energy Minister Gwede Mantashe reported that the bid submission deadline for Bid Window Six (BW6) of the Renewable Energy Independent Power Producer Procurement Programme would be delayed by between 45 and 60 days to ensure procedural fairness in light of President Cyril Ramaphosa’s announcement that the size of the round would be doubled from 2 600 MW to 5 200 MW.

The bid submission date for BW 6 was initially set down for August 11, after the request for proposals (RFP) documentation was published on April 6.

Speaking during a briefing of the newly established Energy Crisis Committee, Mantashe said it would be “unfair to expect people to bid for double the capacity if they’re not given the notice”. However, government still needed to make a final decision on the duration of the extension.

He said a formal notice of the extension would be made soon.

In July, Eskom’s Grid Access

You’ve reached your free article limit

Subscribe to enjoy unlimited access to trusted journalism. Cancel anytime.

Subscribe now

Need help? molokom@insidepolitic.co.za

More articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Inside Education E-edition August 2026

spot_img

Services Seta 2026

spot_img

CATHSSETTA

spot_img

AVBOB STEP 12

spot_img

Inside Metros G20 COJ Edition

spot_img

JOZI MY JOZI

spot_img

QCTO

spot_img

Latest article