Johnathan Paoli
Eskom has confirmed the addition of more megawatts of power following the successful synchronisation into the national grid of Unit 5 of the Kusile power plant.
Eskom spokesperson Daphne Mokoena said on Sunday the unit is expected to contribute an additional 800 megawatts to the national power system.
Mokoena said that the unit will supply electricity intermittently during the testing and optimisation phase over the next six months before being transferred into commercial operation and the capacity officially added to the current Eskom fleet.
The power utility’s Group Executive for Generation Bheki Nxumalo said as part of the Generation Recovery Plan, the synchronisation of the unit marked another significant milestone of sustainably improving generation performance as well as contributing the much needed power to the grid.
“We are encouraged that this achievement of our recovery plan immediately follows the return of the three units that were brought online